Preliminary Timeline for Greenlight Fiber-to-the-Home Project

Mark Murphy, Managing Partner of Greenlight Networks, has provided this tentative timeline for the fiber-to-the-home project:

  • Engineering work -- COMPLETE.
  • Permits & utility licenses -- In progress.
  • Begin accepting customer deposits: Mid-to-late August.
    Greenlight will email Meadowbrook residents who have signed-up on the website.
  • Deposit period closes: August 31.
    All Meadowbrook residents who submit a deposit by this time will receive free installation.
  • Begin network construction: Mid-to-late September.
    You will see our crews hanging fiber on the telephone poles.
  • Begin home installations: Early-to-mid October.
    We will set up an appointment to complete the installation work inside your home.
  • Installations complete: Mid-to-late October.

Please note that the permitting and licensing phase is the least predictable element of the plan -- the bureaucratic work is less predictable than the hardhat work! -- so we should expect an updated timeline in a month or less.

If you have not yet signed up on the Greenlight Networks website, it is not too late to do so. Just click the link below and enter your contact information:
http://greenlightnets.com/sign-up-for-service/
Signing up now does not commit you to anything, but will help make sure that you have a chance to be included in the initial round of installations. Greenlight Networks is seeing a very strong demand for their service, and we expect their installers to get increasingly busy as time goes on.


.
. .

Site development and maintenance by Jim Kane/Simply Effective